1、項目團隊成員之間的工作方式存在沖突。項目經理需要改進成員之間的關系,并定義行為基本規則。項目經理應使用下列哪項?
A、RACI矩陣
B、組織結構圖
C、團隊章程
D、項目團隊派工單
2、項目經理將與提供額外資源完成關鍵項目任務的外部供應商協商合同條款。為了減少項目風險,項目經理應選擇什么合同類型?
A、成本補償合同
B、固定總價合同
C、總價加激勵費用合同
D、工料合同
3、As part of a key project in a large organization,the manufacturing of valves is outsourced to a third party.The project manager learned that the valves will arrive earlier than expected and in greater quantities.What should the project manager d o next?
作為一個大型組織中關鍵項目的組成部分,閥門制造業務被外包給第三方。項目經理得知閥門將比預期更早到達且數量更多。項目經理下一步應該怎么做?
A、Review the project schedule and fast track activities t o complete the project earlier.審查項目進度計劃并快速跟進活動,以便盡早完成項目?;巯杼斓?/p>
B、Adds additional resources close the project earlier update the lessons learned.增加額外資源,盡早結束項目,并更新經驗教訓。慧翔天地
C、Refer to the procurement management plan to review the terms of delivery from the third party.查閱采購管理計劃來審查第三方的交付條件?;巯杼斓?/p>
D、Review of the cost and schedule plan.審查成本和進度計劃。慧翔天地
4、Progressive elaboration is a characteristic of projects that integrate the concepts of temporary and unique in project plan development,progressive elaboration also is terms of()漸進明細是結合了項目的一次性和獨特性的特點。編制項目計劃的過程中,漸進明細在以下哪個方面也是重要的∶()
A、Assumptions假設
B、Constraints限制條件
C、Project management information system項目管理信息系統
D、Organizational policies and procedures組織政策和程序
5、Project team members are used to performing changes outside of the established change control process.In a team meeting,another change request was issued to the company board o f directors.What should the project manager do?
項目團隊成員習慣于在制定好的變更控制過程之外進行變更。在一次團隊會議上,向公司董事會發出另一個變更請求。項目經理應該怎么做?
A、Accept the change request and continue to manage the project to meet its requirements and schedule接受該變更請求,并繼續管理項目以滿足其要求和進度計劃
B、Notify the requester that the change should be handle d through the change control process通知請求者應該通過變更控制過程來處理變更
C、Conduct a team-building session and hope that the tea m gets back on track after all the changes召開—次團隊建設會議,希望團隊在所有變更之后重新走回正軌
D、Ask the project sponsor for details about changes and project performance向項目發起人詢問有關變更和項目績效的詳細信息
(240522)答案
6、D
7、D
8、B
9、A
10、B