1、項目經理聘用一名供應商交付關鍵部件。供應商未能按期交付,項目經理根據合同條款提出索賠,供應商拒絕接受該索賠。項目經理能夠如何解決這種情況?
A、尋求調解員的幫助
B、將該問題上報給項目發起人
C、與該供應商談判
D、將問題提交給法律部門
2、A new project has high uncertainly in the cost required for completion.What approach should the project manager use to determine the expected costs?
一個新項目完工所需成本的不確定性很高項目經理應該用什么方法來確定預期成本?
A、Analogous estimating類比估算
B、Statistical techniques estimating統計技術估算
C、Parametric estimating參數估算
D、Three-Point estimating三點估算
3、A project team is working on a project's new approved scope.The regulatory team was integral in providing input that necessitated this change.However,the team discovers that t he regulatory department was not listed as a project stakeholder.What should the project manager do next?
項目團隊正在研究一個項目的新批準范圍,監管團隊在變更方面提供的意見是不可或缺的.但是,該團隊發現監管部門未被列為項目相關方∶項目經理下一步應該怎么做?
A、Instruct the project team to verify the need for this change.指示項目團隊確認是否需要進行這項變更,
B、Create a new change request and ensure that the regulatory team is involved in the process.創建—項新的變更請求并確保監管團隊參與這個過程
C、Gather further input from the regulatory team and update the existing change request to reflect the new information.收集監管團隊的進一步意見,并更新現有變更請求以反映新信息
D、Ensure that the regulatory team is included in the change control board.確保監管團隊包含在變更控制委員(CCB)中
4、If the end date of an initial plan is later than the desired date,what is the FIRST action the project manager should consider?
如果初步計劃的完工日期遲于期望日期,則項目經理應考慮的第一步行動是什么?
A、Reviewing current resource on the project
評審當前的項目資源情況
B、Determining whether more work can be done in parallel。
確定是否有更多工作能夠并行
C、Starting critical path activities at their early start dates。
在最早開始日期開始關鍵路線活動
D、Negotiating a change in scope for an activities with negative float
為任何負時差活動協商工作范圍變化
5、A control chart shows seven data points in a row on one side of the mean.What should be done?
一控制圖顯示在均值的一側有7個數據點在一條直線上。應采取什么措施?
A、Perform a design of experiments.執行試驗設計
B、Adjust the chart to reflect the new mean.調整控制圖以反映新的均值
C、Find an assignable cause尋找原因
D、Nothing.This is the rule of seven and can be ignored什么都不做,這是7點原則,可以忽略
(241104)答案
6、B
7、D
8、C
9、C
10、D