171、Your cost forecast shows that you will have a cost overrun at the end of the project.Which of the following should you do?
A.Eliminate risks in estimates and re-estimate.
B.Meet with the sponsor to find out what work can be done sooner.
C.Cut quality.
D.Decrease scope.
171、你的成本預測顯示在項目期末時,你的成本會超支。你應采取下列哪項措施
A.消除估算和重估的風險
B.會見出資人找出哪項工作能夠最快完成
C.削減數量
D.減少范圍
172、During the executing phrase of a project,a project team member has difficulties in performing the tasks assigned to them.What should the project manager do?
A.Replace the team member
B.Have a meeting with the team member and provide training if required
C.Escalate the problem to the management
D.Change the baseline to comply with the possible delays
172、在項目執行階段,一名項目團隊成員在執行分配給他的任務時有困難。項目經理應該怎么做
A.更換團隊成員
B.與該團隊成員談話,需要的話提供培訓
C.將問題上報給管理層
D.改變基準以應付可能的延期
173、What diagram is used to illustrate the connections between work to be completed and team resources?
A.Resource histogram
B.Organizational chart
C.Control chart
D.RACI chart
173、下列哪一種圖表示用來說明需要完成的工作與團隊資源之間的關系?
A.資源直方圖
B.組織圖
C.控制圖
D.RACI圖
174、Early in the life of your project,you are having a discussion with the sponsor about what estimating techniques should be used.You want a form of expert judgment,but the sponsor argues for analogous estimating.It would be BEST to:
A.agree to analogous estimating as it is a form of expert judgment.
B.suggest life cycle costing as a compromise.
C.determine why the sponsor wants such an accurate estimate.
D.try to convince the sponsor to allow expert judgment because it is typically more accurate.
174、在項目初期,你和出資人討論關于使用何種估算方法的問題。你想使用專家論證,但是出資人希望采用類比估算。最佳的做法是
A.因為類比估算也是專家論證的一種,所以同意采用類比估算
B.作為讓步,建議采用生命周期成本法
C.弄清楚為什么出資人想用如此精確的估算方法
D.努力說服出資人使用專家論證,因為它更精確
175、You are asked to prepare a budget for completing a project that was started last year and then shelved for six months.All the following would be included in the budget EXCEPT?
A.Fixed costs
B.Sunk costs
C.Direct costs
D.Variable costs
175、公司要你編制一個去年啟動、而后擱置的項目的預算。下列哪項不包括在預算中
A.固定成本
B.沉沒成本
C.直接成本
D.可變成本